Programme of work: Jan 1st 2006 - Dec 31st 2008
Aim 3: |
|
| To consult, develop and support the membership of Belfast Interface Project |
 |
| Current Work Programme: |
|
 |
| Develop Opportunities for peer support |
|
|
Hold Thematic Discussion #3
Hold Thematic Discussion #4
Hold Thematic Discussion #5 |
Completed Sep 06
Completed March 07
Due April 08 |
 |
| Continue to produce 'Interface' newssheet |
|
|
Produce Issue #5
Produce Issue #6
Produce Issue #7
Produce Issue #8
Produce Issue #9
Produce Issue #10 |
Completed April 06
Completed Sep 06
Completed March 07
Completed July 07
Due Jan 08
Due June 08 |
 |
| Update members 'Information' Pack |
On-going |
|
|
|
|
|
 |
| Develop individual, group and associate membership |
On-going |
|
|
 |
| Hold Conferences addressing critical issues |
|
|
Deliver 2006 annual conference
Deliver 2007 annual conference
|
Completed Nov 2006
Due late 07/early 08 |
 |
| Evaluate and adapt BIP/CD joint project |
On-going |
|
|
 |
| Identify further membership needs. |
|
Carry out survey of membership needs
Disseminate survey findings |
Due winter 2007
Due Jan 2008 | |